Guide

August 2026 · Canadian Commercial Mortgages

By Nav Grewal, Principal Broker

Construction draws: how the money actually arrives.

The most expensive misunderstanding in construction financing is thinking of the loan as a lump sum. It isn't. A construction facility is a commitment that pays out in stages, in arrears, against work already completed and verified. Builders who plan cash flow around when money is spent rather than when it is reimbursed run out of it, usually mid project, at the worst possible price.

Engraved illustration of a mid rise building under construction wrapped in scaffolding with a tower crane.

The core principle: cost to complete

At every moment of the project, the lender cares about one number: is there enough undrawn money left to finish the building? That is cost to complete underwriting. Each draw is sized so that remaining facility plus your remaining equity always covers remaining work. It is also why lenders make you spend your own equity first, by the time their money starts flowing, your capital is already in the ground and their loan is protected by finished work.

What a draw schedule really looks like

Schedules are negotiated per project, but a typical ground up deal advances in stages tied to verified completion:

StageTypical cumulative completionWhat the inspector verifies
Land / closeNoneEquity in, permits, budget, fixed price contracts
Draw 1, Foundation~15%Excavation, footings, foundation complete
Draw 2, Lock up~40%Framing, roof, windows, building sealed
Draw 3, Drywall~65%Mechanical, electrical, plumbing roughed in and covered
Draw 4, Completion~85%Finishes, equipment, site works
Final draw100%Occupancy permit, deficiencies cleared, liens clear

Illustrative. Actual stages and percentages vary by project and lender.

Each draw follows the same loop: you request it, a quantity surveyor or cost consultant inspects and reports percentage complete against budget, the lender advances against that verified number, less holdback, and the cycle repeats. The loop typically takes one to three weeks from request to funds, which is the single most important number to build into your trade payment terms.

The 10% you can't have yet

In BC, the Builders Lien Act requires 10% of the value of work to be held back from payments, releasable 55 days after substantial completion. Lenders administer this inside the draw process: every advance arrives net of holdback, and the accumulated 10% lands near the end of the project. Two practical consequences: your trades need to carry that gap in their contracts, and your cash flow model must not count holdback as available funds until release. Ontario and Alberta run equivalent regimes with different release timing.

Interest doesn't wait for completion

Construction facilities are interest only during the build, charged monthly on the drawn balance, which means the carrying cost starts small and compounds toward the end. Most facilities fund this through an interest reserve: a line item in the budget the lender draws against automatically. If the project runs long, the reserve runs out, and topping it up becomes an equity call at the moment you have the least equity to spare. Schedule risk is interest risk.

Why draws stall, and how files are built so they don't

The draw requests that stall share the same patterns: work claimed but not complete at inspection, unpaid trade invoices surfacing as lien risk, change orders that moved the budget without lender sign off, and cost overruns that break the cost to complete math. The fix is mostly structural, and it happens before the first draw: a realistic budget with contingency the lender has already approved, fixed price contracts where possible, a draw schedule matched to how your trades actually invoice, and one person, usually the broker, reconciling the cost consultant's report against the request before it goes in. A clean draw file funds in days; a contested one funds in weeks.

When the draw structure itself is the problem

Some projects don't fit institutional draw discipline, the timeline is too tight for the inspection loop, the project is mid stream and needs rescue capital, or the numbers work but the paperwork doesn't yet. That is bridge and private territory: faster advances, lighter process, higher cost, used for a defined window. And when the building completes and leases, the construction facility hands off to term debt, often an insured refinance if the asset qualifies.

FAQ

Draw questions we hear most.

One to three weeks from request to money, driven by the inspection and the lender's review. Clean files with a reconciled cost consultant report sit at the fast end. Build the cycle time into your trade payment terms so a normal draw never becomes a crisis.

Usually some land or soft cost advance funds at close, but the bulk pays out in arrears against completed work, and your equity goes in first. Plan opening cash flow around your own capital, not the facility.

A lien legislation requirement, 10% of the value of work withheld from every advance, released after the lien period expires following substantial completion (55 days in BC). It protects against trade liens; treat it as unavailable until release.

Building something?

Send us the budget, the timeline and the site. We will structure a facility whose draw schedule matches how your project actually spends money.